wednesday i added another course to the south wall. one final course is due, which needs to be ripped as it's shorter than a full panel. the ripped panels clip into utility trim, but i need to pick up some more of those, which requires the truck to transport those long suckers.

since no rain will find its way up in there, i decided to just move on to the east wall and get to that last course later. i taped up the joints on the east wall wednesday, while katie mowed the backyard with a weed whacker ;)

thursday, i covered the east wall with felt, cut & attached window trim, and trim around the rear sillcock. upper courses of felt went up in 70inch widths from a ladder. i still need j-channel around the rake, and before that i need to trim up the ridge board with a sawzall, since i ran it a little long during framing.

maybe i'll remember the camera tomorrow..