so it's december 12th. time flies, eh.
the windows will be arriving on the 23rd. that's in 11 days. eleven days. what do i need to do before the windows can go in?
- frame the roof.
that's ridgeboard, rafters, gable walls, overhang blocking, fascia boards.
- sheathe the roof.
that's 45' x 16' x 2 - about 48 sheets, 4x8 7/16 OSB, up onto the roof into place.
- eave dripedge.
- paper the roof.
unroll that junk into place, tight, nailed down without it blowing all over.
- gable end dripedge.
- roof/wall intersection step flashing.
- shingle the roof.
about 1450sf, or 15 squares, or 45 bundles of asphalt shingles. up on the roof, chalked straight, nailed into place. including ridge vent cap shingles.
- sheathe the walls.
- paper the walls.
- plumb & square the window openings.
- sill pans in window openings.
ok i ordered the windows too soon. or i need to move my ass.